Ofcom planned broadband deployments: what they mean for UK coverage

Ofcom’s planned-deployments report describes what network operators say they expect to build or upgrade. It is useful context for the direction of UK rollout, but it is not the same thing as a service being available at a particular address today.

The short answer

Ofcom reported full-fibre availability at 82% of UK homes in January 2026. Operators’ plans could take that to 92% by January 2029, but the plans are conditional and do not confirm an individual property’s service date.

82%full-fibre availability, January 2026
92%potential full-fibre availability by January 2029
6,950additional or upgraded FWA masts planned

Availability and plans are different questions

The Connected Nations Spring 2026 update is a snapshot of services that were available in January 2026. The planned-deployments report looks forward from that same point: it collects network operators’ stated plans for the following three years. One is an observed coverage measure; the other is a conditional view of intended build.

That distinction matters when checking a home or business. A plan can move, be revised, overlap with another operator’s network, or be delivered later than expected. Use Ofcom’s coverage checker and a provider’s address checker for an availability decision now; use the plans report to understand the wider rollout context.

The national coverage path Ofcom reported

Ofcom said full fibre was available to 24.9 million UK homes (82%) in January 2026, while gigabit-capable broadband reached 27.1 million homes (89%). If all reported plans are realised, it estimates 28.1 million homes could have full fibre and 29 million could have gigabit-capable coverage by January 2029. These percentages are not a guarantee for any authority, constituency, street, or address.

Full-fibre available now (Ja…82%Full-fibre if plans are real…92%Gigabit-capable now (Jan 202…89%Gigabit if plans are realise…95%
Current UK availability and the conditional national coverage level in Ofcom's planned-deployments report

Current coverage is a January 2026 snapshot; later values are contingent on operator plans being realised.

Source: Ofcom Connected Nations: Planned Network Deployments 2026 As of January 2026 (plans published May 2026)

Full-fibre homes

24.9m (82%) in January 2026

28.1m (92%) by January 2029 if plans are realised

Gigabit-capable homes

27.1m (89%) in January 2026

29.0m (95%) by January 2029 if plans are realised

Fixed wireless plans

About 6,950 masts are planned for addition or upgrade. This is a network plan, not a premises-availability count.

Why Ofcom’s confidence view matters

The report distinguishes between the total plans operators reported and the subset they have higher confidence of achieving. Ofcom says the high-confidence outlook improved from the prior year, even though the total reported build was lower. That is a useful warning against reading one headline percentage as a timetable: planned rollout is a range of commercial and engineering commitments, not a reservation for an address.

What this means for rural and wireless coverage

The plans include fixed wireless access (FWA) networks that intend to extend or upgrade service to at least 100 Mbit/s. FWA can be especially relevant where the cost of bringing fibre to every premise is high, but it remains a separate technology measure from full fibre. Read our FWA guide for the availability definition used in the Connected Nations data and our rural coverage guide for the gaps visible today.

How to use the plans with local data

  1. Start with current availability for your local authority or constituency in PlainBroadband’s authority and constituency data.
  2. Compare two areas in the coverage tool to see today’s full-fibre, gigabit, FWA, and decent-broadband measures on the same basis.
  3. Use the planned-deployments report as contextual evidence only. For an address-level decision, confirm with the relevant provider and Ofcom checker.

Frequently asked questions

Does a planned deployment mean I can order broadband?

No. It records an operator’s intended deployment or upgrade. Availability depends on whether the build has completed and whether a provider can supply the specific address.

Why does the report use January 2029?

The 2026 report starts from a January 2026 data snapshot and considers the following three years. Its national end point is therefore January 2029, even though the report was published in May 2026.

Are the planned percentages a government target?

No. They are Ofcom’s presentation of operator-reported plans. The report explicitly focuses on operators’ expected network deployment rather than separate aspirations or plans held by public authorities.

What to do with this

A planned deployment is not the same as availability today, check current coverage before treating a plan as a reason to wait or switch.

Planned deployments are operator-reported intentions, not guarantees; confirm current availability with a provider or Ofcom checker before making a decision.

The coverage figures and planned-deployment statements on this guide are attributed to Ofcom's May 2026 report. PlainBroadband distinguishes current availability from conditional operator plans and does not make address-level availability promises. Current local profiles continue to use the Ofcom Connected Nations Spring 2026 extract. See our editorial standards & corrections policy, the methodology behind these numbers, or report a data error. Data current as of January 2026.